Or. Admin. R. 137-049-0250

Current through Register Vol. 63, No. 6, June 1, 2024
Section 137-049-0250 - Addenda to Solicitation Documents
(1)Issuance; Receipt. The Contracting Agency may change a Solicitation Document only by Written Addenda. An Offeror shall provide Written acknowledgement of receipt of all issued Addenda with its Offer, unless the Contracting Agency otherwise specifies in the Addenda or in the Solicitation Document.
(2)Notice and Distribution. The Contracting Agency shall notify prospective Offerors of Addenda consistent with the standards of Notice set forth in OAR 137-049-0210(1). The Solicitation Document shall specify how the Contracting Agency will provide notice of Addenda and how the Contracting Agency will make the Addenda available (see, 137-049-0200(1)(a)(N). For example, "Contracting Agency will not mail notice of Addenda, but will publish notice of any Addenda on Contracting Agency's Web site. Addenda may be downloaded off the Contracting Agency's Web site. Offerors should frequently check the Contracting Agency's Web site until closing, i.e., at least once weekly until the week of Closing and at least once daily the week of the Closing."
(3)Timelines; Extensions. The Contracting Agency shall issue Addenda within a reasonable time to allow prospective Offerors to consider the Addenda in preparing their Offers. The Contracting Agency may extend the Closing if the Contracting Agency determines prospective Offerors need additional time to review and respond to Addenda. Except to the extent required by public interest, the Contracting Agency shall not issue Addenda less than 72 hours before the Closing unless the Addendum also extends the Closing.
(4)Request for Change or Protest. Unless a different deadline is set forth in the Addendum, an Offeror may submit a Written request for change or protest to the Addendum, as provided in OAR 137-049-0260, by the close of the Contracting Agency's next business day after issuance of the Addendum, or up to the last day allowed to submit a request for change or protest under 137-049-0260, whichever date is later. The Contracting Agency shall consider only an Offeror's request for change or protest to the Addendum; the Contracting Agency shall not consider a request for change or protest to matters not added or modified by the Addendum, unless the Offeror submits the request for change or protest before the deadline for the Contracting Agency's receipt of request for change or protests as set forth in 137-049-0260(2) and (3).

Or. Admin. R. 137-049-0250

DOJ 11-2004, f. 9-1-04, cert. ef. 3-1-05

Stat. Auth.: ORS 279A.065

Stats. Implemented: ORS 279C.395 & 279A.065