Or. Admin. Code § 137-048-0250

Current through Register Vol. 63, No. 12, December 1, 2024
Section 137-048-0250 - Solicitation Cancellation, Delay or Suspension; Rejection of All Proposals or Responses; Consultant Responsibility For Costs

A Contracting Agency may cancel, delay or suspend a solicitation, RFQ or other preliminary Procurement document, whether related to a Direct Appointment Procedure (OAR 137-048-0200), the Informal Selection Procedure (OAR 137-048-0210), and the Formal Selection Procedure (OAR 137-048-0220), or reject all Proposals, responses to RFQs, responses to other preliminary Procurement documents, or any combination of the foregoing, if the Contracting Agency believes it is in the public interest to do so. In the event of any such cancellation, delay, suspension or rejection, the Contracting Agency is not liable to any Proposer for any loss or expense caused by or resulting from any such cancellation, delay, suspension or rejection. Consultants responding to either solicitations, RFQs or other preliminary Procurement documents are responsible for all costs they may incur in connection with submitting Proposals, responses to RFQs or responses to other preliminary Procurement documents.

Or. Admin. Code § 137-048-0250

DOJ 11-2004, f. 9-1-04, cert. ef. 3-1-05; DOJ 20-2005, f. 12-27-05, cert. ef. 1-1-06; DOJ 19-2007, f. 12-28-07, cert. ef. 1-1-08; DOJ 15-2009, f. 12-1-09, cert. ef. 1-1-10; DOJ 10-2011, f. 11-29-11, cert. ef. 1-1-12

Stat. Auth.: ORS 279A.065

Stats. Implemented: ORS 279A.065, 279C.110