Or. Admin. Code § 123-042-0065

Current through Register Vol. 63, No. 12, December 1, 2024
Section 123-042-0065 - Allowable Project Costs

For purposes of projects funded under this division of rules, the allowable costs of a project include:

(1) Financing costs, including capitalized interest;
(2) Direct project management costs;
(3) Costs of consultant services and expenses;
(4) Construction costs and expenses;
(5) Costs of property acquisition, including any easement, or right of way directly related to and necessary for the project;
(6) Costs incurred by the municipality prior to the award if such costs are allowable under the authority's adopted policy for reimbursement of pre-award costs;
(7) Costs of acquiring off-site property for purposes directly related to the project, such as wetland mitigation; and
(8) Other costs that the authority determines to be necessary or useful.

Or. Admin. Code § 123-042-0065

EDD 10-2006, f. & cert. ef. 11-1-06; OBDD 41-2010, f. 11-30-10, cert. ef. 12-1-10

Stat. Auth.: ORS 285B.419 & 285A.075

Stats. Implemented: ORS 285B.410 - 285B.482