Current through Register Vol. 64, No. 1, January 1, 2025
Section 123-027-0161 - Non-Federal Project Application Review and ApprovalTo approve an application for assistance from the fund, the Authority must make the determinations as follows:
(1) The project is an eligible project. If the Authority determines that the project is not eligible, it may reject an application or require further documentation from the Port;(2) The requisite need for the project has been demonstrated to the Authority in the application or the local planning process;(3) If application is for a loan, the loan security includes the pledge of revenues and/or other funds, and is sufficient, when considered with other security, to assure repayment;(4) The Port is willing and able to enter into a contract with the Authority; and(5) Moneys in the fund are or will be available for the project.Or. Admin. Code § 123-027-0161
EDD 22-2004, f. & cert. ef. 8-19-04; EDD 2-2006, f. & cert. ef. 2-10-06; EDD 19-2009, f. 10-30-09, cert. ef. 11-1-09Stat. Auth.: ORS 285A.075
Stats. Implemented: ORS 777.262 - 777.267