Section 785:50-9-38 - Construction phase(a)Inspection during construction. During the building phase of the project, the recipient shall provide independent engineering or other professional services necessary to assure completion of the project in accordance with the loan agreement and the approved plans and specifications. (b)Resident inspection. After the construction contract is awarded, the recipient shall provide for adequate full-time independent resident inspector of the project and require assurance that the work is being performed in a satisfactory manner in accordance with the approved plans and specifications, approved alterations, and in accordance with sound engineering principles and building practices. The Board is authorized to inspect the building of any project at any time in order to assure that plans and specifications are being followed and that the works are being built in accordance with sound engineering principles and building practices, but such inspection shall never subject the State of Oklahoma to any action for damages. The Board shall bring to the attention of the recipient and the project engineer any variances from the approved plans and specifications. The recipient and the project engineer shall immediately initiate necessary action rectifying construction deficiencies. (c)Inspection of materials.(1) The Board is also authorized to inspect all materials furnished, including inspection of the preparation or manufacture of the materials to be used. The state inspector is to report the manner and progress of the building or to report conditions relating to the materials furnished and the compliance by the contractor with approved plans and specifications for the project. Such inspection will not release the contractor from any obligation to perform the work in accordance with the requirements of the contract documents or the project engineer from determining compliance with the requirements of the contract documents.(2) In the event building procedures or materials are determined by the Board to be substandard or otherwise unsatisfactory and/or not in conformity with approved plans and specifications, the Board may order the recipient to take such action in the manner provided for in the construction contract to correct any such deficiency.(3) In those instances of dispute between the recipient project engineer and the Board's representative as to whether material furnished or work performed conforms with the terms of the construction contract, the Board may order the recipient to direct the project engineer to reject questionable materials and/or initiate other action provided for in the construction contract, including suspension where necessary, until all disputed issues are resolved in accordance with the terms of the construction contract.(4) The contractor and recipient shall furnish the Board's representative with every reasonable facility for ascertaining whether the work as performed is in accordance with the requirements and intent of the contract.(5) In addition to normal testing procedures required of the recipient, the Board may require reasonable additional tests of building materials of processes which the Board determines to be necessary during the building of projects financed in whole or in part by Clean Water SRF funds. All tests, whether for the Board or the project engineer, will conform to current American Water Works Association, American Association of State Highway and Transportation Officials, American Society of Testing and Materials, and the Oklahoma Department of Transportation published procedures, or similar criteria. The Board shall specify which tests are applicable. Samples for testing shall be furnished free of cost to the Board upon request on the construction site.Okla. Admin. Code § 785:50-9-38
Added at 10 Ok Reg 3333, eff 7-1-93; Amended at 15 Ok Reg 2881, eff 7-1-98; Amended at 17 Ok Reg 2772, eff 7-1-00; Amended at 26 Ok Reg 1715, eff 6-11-09Amended by Oklahoma Register, Volume 31, Issue 24, September 2, 2014, eff. 9/12/2014Amended by Oklahoma Register, Volume 32, Issue 24, September 1, 2015, eff. 9/11/2015Amended by Oklahoma Register, Volume 35, Issue 24, September 4, 2018, eff. 9/14/2018