Section 753:11-9-1 - Registration of Construction Managers

All Construction Managers desiring to perform services for the Trust must be registered with OMES. Any Construction Manager not registered with OMES at the time the Trust announces a project may register with OMES and submit a letter of interest to the Trust. All Construction Managers desiring to perform services for the Trust that are funded using federal dollars must be registered with SAM.gov, obtain a Unique Entity Identifier, and shall not be on the federal debarred supplier listing.

Okla. Admin. Code § 753:11-9-1

Adopted by Oklahoma Register, Volume 36, Issue 24, September 3, 2019, eff. 9/18/2019
Amended by Oklahoma Register, Volume 40, Issue 23, August 15, 2023, eff. 9/1/2023