This inspection shall occur upon completion of construction and when requested by the contractor after he determines the project is finally complete and all punch list items have been completed. The CFMO or his designee and/or Design Consultant shall send out formal notification inviting the ADC and other interested parties to attend.
Okla. Admin. Code § 752:11-7-16