Okla. Admin. Code § 730:10-3-4

Current through Vol. 42, No. 8, January 2, 2025
Section 730:10-3-4 - Incomplete projects

Any county Surface Transportation Program or bridge replacement project that has not progressed through the design stage and right-of-way acquisition and is not ready to let to contract within two years after the date of receipt of the programming resolution may be canceled by the Department and all federal funds intended for the project shall be available through the Department to other counties.

Okla. Admin. Code § 730:10-3-4

Amended at 17 Ok Reg 1368, eff 5-11-00