Section 730:10-15-2 - Project development process(a) The Department shall establish and maintain meaningful project schedules, establish accountability for project components, manage the construction program and measure performance. Since it is not possible to create a single project development process or schedule that will prove effective for every project every time, the Department shall establish a milestone based project schedule for each project identified in the Eight Year Construction Work Plan.(b) As more detailed information becomes available during the course of project development, the Department shall facilitate necessary modifications to the scope, schedule and/or budgets of approved Eight Year Construction Work Plan projects through a formal revision process.Okla. Admin. Code § 730:10-15-2