Okla. Admin. Code § 252:633-3-21

Current through Vol. 41, No. 19, June 17, 2024
Section 252:633-3-21 - Building phase submittals

The following submittal and accompanying actions by the recipient are required during and upon the completion of the construction of the project;

(1) Any change order shall be submitted to the DEQ for approval;
(2) Once construction is completed, notice shall be submitted to the DEQ; and
(3) A complete set of as-built drawings shall be submitted to the DEQ upon completion of construction.

Okla. Admin. Code § 252:633-3-21

Added at 14 Ok Reg 1139, eff 3-18-97 (emergency); Added at 14 Ok Reg 1690, eff 6-2-97; Amended at 15 Ok Reg 1957, eff 6-1-98; Amended at 25 Ok Reg 1140, eff 7-1-08