Okla. Admin. Code § 252:616-13-2

Current through Vol. 41, No. 19, June 17, 2024
Section 252:616-13-2 - Pre-closure sampling and analysis plan

A pre-closure sampling and analysis plan shall be submitted to the DEQ at least 30 days prior to any pre-closure sampling. The plan shall include a copy of the monitoring plan and any monitoring data. Pre-closure sampling activities shall not begin until the facility has received written approval from the DEQ.

Okla. Admin. Code § 252:616-13-2

Added at 17 Ok Reg 1925, eff 6-12-00