Okla. Admin. Code § 252:517-15-4

Current through Vol. 42, No. 4, November 1, 2024
Section 252:517-15-4 - Final closure
(a)DEQ approval required. The DEQ must approve the final closure of a CCR unit before the post-closure period can begin.
(b)Extension of closure period. The DEQ may extend the closure period and require the posting of additional financial assurance if:
(1) any testing shows the confirmed presence of elevated levels of any constituent;
(2) any evidence of contamination related to site operations has been found; or
(3) final closure of the site is found to be inadequate.

Okla. Admin. Code § 252:517-15-4

Adopted by Oklahoma Register, Volume 33, Issue 24, September 1, 2016, eff. 9/15/2016