Okla. Admin. Code § 252:517-13-4

Current through Vol. 42, No. 7, December 16, 2024
Section 252:517-13-4 - Inspection requirements for CCR surface impoundments
(a)Inspections by a qualified person.
(1)Inspection intervals. All CCR surface impoundments and any lateral expansion of a CCR surface impoundment must be examined by a qualified person as follows:
(A) At intervals not exceeding seven days, inspect for any appearances of actual or potential structural weakness and other conditions which are disrupting or have the potential to disrupt the operation or safety of the CCR unit;
(B) At intervals not exceeding seven days, inspect the discharge of all outlets of hydraulic structures which pass underneath the base of the surface impoundment or through the dike of the CCR unit for abnormal discoloration, flow or discharge of debris or sediment; and
(C) At intervals not exceeding 30 days, monitor all CCR unit instrumentation.
(D) The results of the inspection by a qualified person must be recorded in the facility's operating record as required by OAC 252:517-19-1(g)(5).
(2)Timeframes for inspections by a qualified person.
(A)Existing CCR surface impoundments. The owner or operator of the CCR unit must have initiated the inspections required under paragraph (a) of this Section no later than October 19, 2015.
(B)New CCR surface impoundments and any lateral expansion of a CCR surface impoundment.

The owner or operator of the CCR unit must initiate the inspections required under paragraph (a) of this Section upon initial receipt of CCR by the CCR unit.

(b)Annual inspections by a qualified professional engineer.
(1)Inspection requirements. If the existing or new CCR surface impoundment or any lateral expansion of the CCR surface impoundment is subject to the periodic structural stability assessment requirements under OAC 252:517-11-4(d) or OAC 252:517-11-5(d), the CCR unit must additionally be inspected on a periodic basis by a qualified professional engineer to ensure that the design, construction, operation, and maintenance of the CCR unit is consistent with recognized and generally accepted good engineering standards. The inspection must, at a minimum, include:
(A) A review of available information regarding the status and condition of the CCR unit, including, but not limited to, files available in the operating record (e.g., CCR unit design and construction information required by OAC 252:517-11-4(c)(1) and OAC 252:517-11-5(c)(1), previous periodic structural stability assessments required under OAC 252:517-11-4(d) and OAC 252:517-11-5(d), the results of inspections by a qualified person, and results of previous annual inspections);
(B) A visual inspection of the CCR unit to identify signs of distress or malfunction of the CCR unit and appurtenant structures; and
(C) A visual inspection of any hydraulic structures underlying the base of the CCR unit or passing through the dike of the CCR unit for structural integrity and continued safe and reliable operation.
(2)Inspection report. The qualified professional engineer must prepare a report following each inspection that addresses the following:
(A) Any changes in geometry of the impounding structure since the previous annual inspection;
(B) The location and type of existing instrumentation and the maximum recorded readings of each instrument since the previous annual inspection;
(C) The approximate minimum, maximum, and present depth and elevation of the impounded water and CCR since the previous annual inspection;
(D) The storage capacity of the impounding structure at the time of the inspection;
(E) The approximate volume of the impounded water and CCR at the time of the inspection;
(F) Any appearances of an actual or potential structural weakness of the CCR unit, in addition to any existing conditions that are disrupting or have the potential to disrupt the operation and safety of the CCR unit and appurtenant structures; and
(G) Any other change(s) which may have affected the stability or operation of the impounding structure since the previous annual inspection.
(3)Timeframes for conducting the initial inspection.
(A) Existing CCR surface impoundments. The owner or operator of the CCR unit must have completed the initial inspection required by paragraphs (b)(1) and (2) of this Section no later than January 19, 2016.
(B) New CCR surface impoundments and any lateral expansion of a CCR surface impoundment. The owner or operator of the CCR unit must complete the initial annual inspection required by paragraphs (b)(1) and (2) of this Section is completed no later than 14 months following the date of initial receipt of CCR in the CCR unit.
(4)Frequency of inspections.
(A) Except as provided for in paragraph (b)(4)(B) of this Section, the owner or operator of the CCR unit must conduct the inspection required by paragraphs (b)(1) and (2) of this Section on an annual basis. The date of completing the initial inspection report is the basis for establishing the deadline to complete the first subsequent inspection. Any required inspection may be conducted prior to the required deadline provided the owner or operator places the completed inspection report into the facility's operating record within a reasonable amount of time. In all cases, the deadline for completing subsequent inspection reports is based on the date of completing the previous inspection report. For purposes of this Section, the owner or operator has completed an inspection when the inspection report has been placed in the facility's operating record as required by OAC 252:517-19-1(g)(6).
(B) In any calendar year in which both the periodic inspection by a qualified professional engineer and the quinquennial (occurring every five years) structural stability assessment by a qualified professional engineer required by OAC 252:517-11-4(d) and OAC 252:517-11-5(d) are required to be completed, the annual inspection is not required, provided the structural stability assessment is completed during the calendar year. If the annual inspection is not conducted in a year as provided by this paragraph (b)(4)(B), the deadline for completing the next annual inspection is one year from the date of completing the quinquennial structural stability assessment.
(5)Deficiency identified; corrective measures taken. If a deficiency or release is identified during an inspection, the owner or operator must remedy the deficiency or release as soon as feasible and prepare documentation detailing the corrective measures taken.
(6)DEQ notification. The DEQ shall be notified if a deficiency is identified in (5) above and provided documentation of corrective measures.
(c)Recordkeeping. The owner or operator of the CCR unit must comply with the recordkeeping requirements specified in OAC 252:517-19-1(g), the notification requirements specified in OAC 252:517-19-2(g), and the internet requirements specified in OAC 252:517-19-3(g).

Okla. Admin. Code § 252:517-13-4

Adopted by Oklahoma Register, Volume 33, Issue 24, September 1, 2016, eff. 9/15/2016
Amended by Oklahoma Register, Volume 35, Issue 24, September 4, 2018, eff. 9/15/2018