Section 252:515-41-15 - Closure
(a)Closure plan. Roofing material recycling facilities shall submit, with their permit application, a closure plan addressing the following items:
(1) removal and disposal of all roofing material permitted to be stored on site;
(2) removal of equipment and temporary buildings and other improvements not designated as permanent in the permit application; and
(3) grading and re-vegetation of the site.
(b)Cost estimates. Cost estimates for closure shall be based upon the cost for removal and disposal, by a third party not affiliated with the owner/operator, of the maximum amount of roofing material permitted to be stored on site at any time, removal of equipment, temporary buildings, and re-vegetation.
(c)Closure cost estimate procedures. The following determinations shall be submitted to DEQ for approval:
(1) identification of the task(s) for which bids will be provided;
(2) a statement of work fully describing the actions necessary for completion of the task(s) identified; and
(3) written bids from three independent contractors not affiliated with the owner/operator. The bids shall be dated within 30 days of submittal and be an estimate of the contractor's cost for performing the work identified in the statement of work on behalf of the State of Oklahoma. The closure cost estimate shall be calculated as the average of the bids.