Section 252:515-3-1 - Permit required
(a)Solid waste disposal facilities. The following solid waste disposal facilities are subject to the requirements of this Subchapter and require a solid waste permit from DEQ prior to construction and/or operation:
(1) land disposal facilities;
(2) solid waste processing facilities, including:
(A) transfer stations;
(B) solid waste incinerators receiving waste from off-site sources;
(C) regulated medical waste processing facilities receiving waste from off-site sources, and that are not shared service facilities;
(D) used tire facilities;
(E) composting facilities, except special events composting facilities and other facilities exempted by OAC 252:515-43-31;
(F) permanently established household hazardous waste collection facilities; and
(G) any other type of facility that processes solid waste;
(3) facilities used for the storage of solid waste for longer than 10 days; and
(4) facilities used for the storage of more than 50 used tires, except as authorized by 27A O.S. § 2-11-401.7.
(b)Sludge. Solid waste disposal facilities used for the beneficial use, transport, disposal, or storage of sludge that is not subject to the direct jurisdiction of any other environmental regulatory agency of the State of Oklahoma shall obtain a permit in accordance with OAC 252:515-3-41.

Okla. Admin. Code § 252:515-3-1

Added at 20 Ok Reg 1151, eff 6-1-03; Amended at 23 Ok Reg 1751, eff 6-15-06; Amended at 29 Ok Reg 1005, eff 7-1-12