Current through Vol. 41, No. 19, June 17, 2024
Section 252:515-25-35 - Final closure(a)DEQ approval required. The DEQ must approve the final closure of a facility before the post-closure period can begin.(b)Extension of closure period. The DEQ may extend the closure period and require the posting of additional financial assurance if:(1) any testing shows the confirmed presence of elevated levels of any constituent;(2) any evidence of contamination related to site operations has been found; or(3) final closure of the site is found to be inadequate.Okla. Admin. Code § 252:515-25-35
Added at 20 Ok Reg 1151, eff 6-1-03