Current through Vol. 42, No. 4, November 1, 2024
Section 252:515-13-2 - Corrective action required(a)Corrective action required. In the event the leachate collection system fails to perform as designed and approved by the DEQ, a corrective action plan shall be submitted to the DEQ within 30 days from the discovery of the failure.(b)Implementation. The corrective action plan shall be implemented within 30 days of DEQ approval.Okla. Admin. Code § 252:515-13-2
Added at 20 Ok Reg 1151, eff 6-1-03