Section 252:515-11-5 - Notification of construction
(a)Notification required. The DEQ shall be notified at least two weeks before liner construction begins. The notification shall:
(1) define the area to be constructed;
(2) include the names of the contractors and the QA and QC officials; and
(3) include results of the pre-construction tests identified in OAC 252:515-11-32(a) when constructing a reconstructed clay liner.
(b)Pre-construction meeting. A pre-construction meeting shall be held at the facility with the design engineer and QA and QC officials before liner construction begins. The DEQ shall be notified at least 48 hours in advance of the meeting.

Okla. Admin. Code § 252:515-11-5

Added at 20 Ok Reg 1151, eff 6-1-03