Okla. Admin. Code § 252:4-7-31

Current through Vol. 42, No. 1, September 16, 2024
Section 252:4-7-31 - Air quality time lines

The following air quality permits and authorizations shall be technically reviewed and issued or denied within the time frames specified below.

(1) Construction permits:
(A) PSD and Part 70 Sources - 365 days.
(B) Minor Facilities - 180 days.
(2) Operating permits:
(A) Part 70 Sources - 540 days.
(B) Minor Facilities - 365 days.
(3) Relocation permits - 30 days.

Okla. Admin. Code § 252:4-7-31

Added at 18 Ok Reg 1922, eff 6-11-01