Section 252:100-17-96 - Standards for OSWI operator training and qualification requirements
(a) The OSWI operator training and qualification requirements in 40 CFR 60.2905, 60.2907, 60.2908, 60.2909, 60.2910 except for 60.2910(b)(1), and 60.2911 are hereby incorporated by reference, as they exist on December 16, 2005.
(b) The operator training course must be completed by the latest of the three dates specified in OAC 252:100-17-96(b)(1) through (3).
(1) Final Compliance date.
(2) Six months after OSWI unit startup.
(3) Six months after an employee of the owner/operator assumes responsibility for operating the OSWI unit or assumes responsibility for supervising the operation of the OSWI unit.
(c) The initial review of documentation required to be kept on site as required in 40 CFR 60.2910 must be conducted by the latest of three dates specified in OAC 252:100-17-96(c)(1) through (3).
(1) Final Compliance date.
(2) Six months after OSWI unit startup.
(3) Six months after an employee assumes responsibility for operating the OSWI unit or assumes responsibility for supervising the operation of the OSWI unit.