Section 165:35-45-5 - Commission consideration
(a) PUD shall review and may investigate all wind energy facility information reported or submitted for compliance with the annual reporting requirements in this Subchapter or in 17 O.S. § 160.18 or with the notice requirements in this Subchapter or in 17 O.S. § 160.20 or 17 O.S. § 160.21.
(b) After receiving a report or submission from a wind energy facility pursuant to the annual reporting requirements in this Subchapter or in 17 O.S. § 160.18 or the notice requirements in this Subchapter regarding notice of intent to construct in 17 O.S. § 160.20 or 17 O.S. § 160.21, PUD will:
(1) Determine whether the report or submission is compliant with the annual reporting or notice requirements; and
(2) Inform the wind energy facility owner or operator of PUD's determination within thirty (30) calendar days of receipt of the report or submission if it is not in compliance. In the event PUD determines the wind energy facility's report or submission is not in compliance, PUD shall contact the owner or operator to require additional information; and, such information shall be provided within fifteen (15) calendar days of such notice. If the facility owner fails to correct such non-compliance, PUD may reject the report or submission and may open an investigation to inquire further into the reported or submitted information.

Okla. Admin. Code § 165:35-45-5

Adopted by Oklahome Register, Volume 33, Issue 23, August 15, 2016, eff. 8/25/2016
Amended by Oklahoma Register, Volume 36, Issue 21, July 15, 2019, eff. 7/25/2019