Okla. Admin. Code § 165:35-38-2

Current through Vol. 41, No. 19, June 17, 2024
Section 165:35-38-2 - Application and Scope of Subchapter
(a) This Subchapter is applicable to all electric utilities operating within the State of Oklahoma under the jurisdiction of the Commission.
(b) These cost recovery rules are promulgated to establish processes, procedures, enforcement, reporting, and monitoring provisions that apply to electric utilities regarding the expenditures referenced in 165:35-38-1.
(c) The intention of this Subchapter includes, but is not limited to:
(1) The provision of rules for the recovery of costs associated with transmission upgrades, environmental facilities installed at generation facilities, generation assets constructed by the utility, and generation assets acquired by the utility; and
(2) The protection of customers of a utility from imprudent financial obligations or costs.
(d) All amounts subject to recovery are subject to Commission audit and review. The Commission will resolve any disputes regarding this Subchapter.

Okla. Admin. Code § 165:35-38-2

Added at 23 Ok Reg 699, eff 2-17-06 (emergency); Added at 23 Ok Reg 1666, eff 7-1-06