Okla. Admin. Code § 165:35-23-3

Current through Vol. 41, No. 19, June 17, 2024
Section 165:35-23-3 - Replacement of meters
(a) A request from a consumer for replacement of the service meter on his/her premises because of alleged inaccuracy of the meter shall be deemed a request for the test of the meter, pursuant to OAC 165:35-15-20.
(b) The utility shall make no charge for initial connection of electric service for a consumer except the charges specified in the approved tariffs and rules of service of the utility; provided that for each disconnection and reconnection of service requested for the same consumer at the same location within twelve (12) months after the most recent connection of service, the utility may make a charge prescribed in its approved tariffs.

Okla. Admin. Code § 165:35-23-3

Amended by Oklahoma Register, Volume 31, Issue 24, September 2, 2014, eff. 9/12/2014