Section 165:26-1-48 - [Effective 10/1/2024] Tank and line tightness testing
(a) Tank and line tightness test results in which any part of the tank system tested does not pass must be reported to PSTD within twenty-four (24) hours by the owner, operator, their employees or agents, and also independently by the person or company performing the test. Complete test results must be submitted within seven (7) days of the testing.
(b) Hydrostatic line tightness tests and line leak detector tests must be conducted by a licensed tester, if applicable, in accordance with manufacturer's instructions, and reported on the prescribed PSTD form.
(c) The licensed tester performing line and leak detector tests must also certify that the line leak detector is installed properly.
(d) All personnel performing tank and line testing must have the required license, education, experience, applicable certification, knowledge and competence to correctly perform testing services in accordance with the testing equipment, manufacturer certification and applicable industry standards or codes.
(e) Tank, line and line leak detector testing must be scheduled by submitting the PSTD scheduling form in the established online format and PSTD staff may be present.

Okla. Admin. Code § 165:26-1-48

Renumbered from 165:26-3-17 at 23 Ok Reg 2297, eff 7-1-06; Amended at 25 Ok Reg 2187, eff 7-11-08
Amended by Oklahoma Register, Volume 31, Issue 24, September 2, 2014, eff. 9/12/2014
Amended by Oklahoma Register, Volume 32, Issue 23, August 17, 2015, eff. 8/27/2015
Amended by Oklahoma Register, Volume 35, Issue 24, September 4, 2018, eff. 10/1/2018
Amended by Oklahoma Register, Volume 41, Issue 23, August 15, 2024, eff. 10/1/2024