Okla. Admin. Code § 150:10-1-4

Current through Vol. 42, No. 7, December 16, 2024
Section 150:10-1-4 - Certification
(a) An industrial park certifying team will consist of two (2) representatives from each of the two (2) sponsoring organizations (identified in 150:10-1-3(b) ) and one or more Department of Commerce staff personnel.
(b) The team shall review the application form for completeness of information. The certifying team shall meet with the park developer and review the application and supporting documents to verify all information.
(c) The industrial park may be personally inspected by the certifying team.
(d) Upon meeting all minimum requirements of the certifying team pursuant to the rules of this chapter, the Industrial Park shall receive a Certification from the Oklahoma Department of Commerce.
(e) Any park not achieving certification shall be entitled to a 180-day grace period to accomplish meeting the criteria. The certifying team may aid in this effort. If the necessary improvements are not made within one-hundred and eighty (180) days, a new application must be submitted when the industrial park meets the certification criteria.
(f) A Certification shall be sent to the developer by the Department of Commerce within ten (10) days of certification approval by the Team.

Okla. Admin. Code § 150:10-1-4