An applicant considering construction of a major utility facility or economically significant wind farm may request a preapplication meeting with the board staff prior to submitting an application. The results of such meeting(s) in no way constitutes approval or disapproval of a particular site or route, and in no way predetermines the board's decision regarding subsequent certification or approval.
Ohio Admin. Code 4906-3-02
Five Year Review (FYR) Dates: 3/13/2024 and 05/20/2029
Promulgated Under: 111.15
Statutory Authority: 4906.03, 4906.20
Rule Amplifies: 4906.03, 4906.04, 4906.06, 4906.10, 4906.13, 4906.20
Prior Effective Dates: 12/27/1976, 06/10/1989, 08/28/1998, 12/15/2003, 01/25/2009, 05/07/2009, 12/11/2015