Section 3344-65-21 - Approval of purchase orders and change orders
(A) Purchase orders are evaluated and approved by project, by vendor. Purchases over the bid threshold require a competitive bidding or selection process pursuant to rule 3344-65-16 of the Administrative Code.
(B) Purchase orders, including modifications, require the following approvals:

$$99,999 or less

associate director of purchasing operations or if position is vacant, an employee in purchasing services designated by the controller

$100,000-$200,000

Controller

$200,001 - $649,999

senior vice president for business affairs and finance

$650,000 - $999,999

university president

$1,000,000 or more

board of trustees

(C) Approval authority is based on the total amount of the purchase .
(D) Execution of contracts for purchases are governed by rule 3344-66-01 of the Administrative Code.