N.D. Admin. Code 89-02-01-09.12

Current through Supplement No. 394, October, 2024
Section 89-02-01-09.12 - Extending time to complete construction of drain

If the two-year period expires before construction is complete, the permit recipient may make a written request to the board for a one-year extension. Only two extensions may be granted. All requests for extensions must be made at least sixty days before the expiration date and must specifically state why construction has not been completed. If the request is for an extension relating to a permit of statewide or interdistrict significance, the extension must be submitted to and approved by both the director and the board.

N.D. Admin Code 89-02-01-09.12

Effective February 1, 1997; amended effective April 1, 2004.
Amended by Administrative Rules Supplement 2015-355, January 2015, effective 1/1/2015.
Amended by Administrative Rules Supplement 2022-387, January 2023, effective 1/1/2023.

General Authority: NDCC 61-03-13

Law Implemented: NDCC 61-32-03