N.D. Admin. Code 69-09-08-07

Current through Supplement No. 393, July, 2024
Section 69-09-08-07 - Registration and certification of renewable energy facilities

To be awarded renewable energy certificates, a designated representative must complete the registration process described in this section.

1. The designated representative shall register with the program administrator each renewable energy generation unit. At a minimum, the registration must include the location, owner, technology, rated capacity of the facility, and evidence that the facility meets the resource eligibility criteria in North Dakota Century Code section 49-02-25.
2. After verifying the information required in the registration process for renewable facilities, the program administrator shall create a renewable energy certificate account for the designated representative of the renewable energy resource.
3. The commission or its program administrator may make onsite visits to any registered unit of a renewable energy resource and may revoke the registration of any unit not in compliance with applicable law and rules.
4. A renewable energy facility may not be awarded renewable energy certificates under this program if it is not registered.
5. Any disputes will be resolved using dispute resolution procedures established by the commission or its program administrator.

N.D. Admin Code 69-09-08-07

Effective July 1, 2006.

General Authority: NDCC 49-02-01, 49-02-24, 49-02-25, 49-02-26

Law Implemented: NDCC 49-02-24, 49-02-25, 49-02-26