N.D. Admin. Code 69-09-02-10

Current through Supplement No. 393, July, 2024
Section 69-09-02-10 - Meter readings
1. Readings of all meters used for determining charges to customers shall be made each month. The term "month" means the period between any two consecutive regular meter reading dates, which shall be as nearly as practicable at thirty-day intervals. The meter reading date may be advanced or postponed not more than five days without adjustment of the billing for the period.
2. The utility may read meters used for determining charges to customers less frequently than once each month provided authorization thereof is obtained from the commission.
3. The utility may obtain the meter readings on a form supplied to the customer provided a utility representative reads the meter at least once each three months, and when there is a change of occupancy of the premises, unless otherwise authorized by the commission.
4. Records of all meter readings shall be maintained for a period of six years.

N.D. Admin Code 69-09-02-10

General Authority: NDCC 49-02-11

Law Implemented: NDCC 49-02-11