The commission or its authorized representative may extend the time for abatement or for accomplishment of an interim step, if the failure to meet the time previously set was not caused by lack of diligence on the part of the permittee or operator. The total time for abatement may not exceed ninety days from the date of issuance.
N.D. Admin Code 69-05.2-28-06
General Authority: NDCC 38-14.1-03
Law Implemented: NDCC 38-14.1-28