Section 69-05.2-16-15 - Performance standards - Hydrologic balance -Protection of ground water recharge capacity

Surface mining activities must restore approximate premining recharge capacity, through restoration of the capability of the reclaimed areas as a whole, excluding coal processing waste and underground development waste disposal areas and fills, to a condition which:

1. Supports the approved postmining land use;
2. Minimizes disturbances to the prevailing hydrologic balance in the mine plan area and in adjacent areas; and
3. Provides a rate of recharge that approximates the premining recharge rate.

N.D. Admin Code 69-05.2-16-15

Effective August 1, 1980; amended effective May 1, 1990.