N.D. Admin. Code 6-02-05-05

Current through Supplement No. 394, October, 2024
Section 6-02-05-05 - Application review

The following process will be used to review applications submitted to the commission.

1. Upon receipt of an application, the commission staff shall determine whether the application is complete and meets the eligibility requirements.
2. The commission staff shall review completed applications for eligible projects and assess their merits using the criteria established by the commission.
3. After receiving the commission staff recommendations, the commission may grant preliminary approval of applications based on the grant review criteria and staff recommendations. A preliminary approval determination is subject to change if any information submitted in the project application changes.
4. The commission shall schedule an annual state grant meeting to obtain additional information about applications, if necessary, and to make final decisions regarding grant approvals. At least one week prior to that meeting, the commission shall provide a list of the grant requests given preliminary approval to all grant applicants. Applicants whose applications received preliminary approval may request a modification of the approved funding prior to the annual state grant meeting.

N.D. Admin Code 6-02-05-05

Adopted by Administrative Rules Supplement 2016-360, April 2016, effective 4/1/2016.

General Authority: NDCC 2-05-06.5

Law Implemented: NDCC 2-05-06.5