Any plan of unitized management or any injection into a reservoir for the purpose of maintaining reservoir pressure or for enhanced recovery operations shall be permitted only by order of the commission after notice and hearing. The application for an order shall include a complete statement of all matters required by North Dakota Century Code section 38-08-09 et seq.
The application shall be submitted to the commission, in duplicate, at least forty-five days prior to the date requested for such hearings and shall be accompanied by all engineering, geological, and other technical exhibits which will be introduced at the hearing.
In addition, the application shall set forth that all the provisions of North Dakota Century Code section 38-08-09.5 have been complied with.
N.D. Admin Code 43-02-03-77
General Authority: NDCC 38-08-09
Law Implemented: NDCC 38-08-09