N.D. Admin. Code 33.1-20-03.1-04

Current through Supplement No. 395, January, 2025
Section 33.1-20-03.1-04 - [Effective until 10/1/2024] Permit application review timeline

Upon receipt of a permit application, the department has one hundred twenty days to review and approve or disapprove the application and notify the applicant of the decision. The department may extend the period an additional one hundred twenty days if the applicant submits a significant change that in the department's judgment requires additional time to review.

N.D. Admin Code 33.1-20-03.1-04

Adopted by Administrative Rules Supplement 370, October 2018, effective 1/1/2019.

General Authority: NDCC 23.1-08-03; S.L.2017, ch.199, § 1

Law Implemented: NDCC 23.1-08-03, 23.1-08-09; S.L.2017, ch.199, § 23