Section 33-24-05-998 - Notification and recordkeeping after an emergency
1. The owner or operator must notify the department and other appropriate state and local authorities, that the facility is in compliance with subsection 2 of section 33-24-05-997 before operations are resumed in the affected areas of the facility.
2. The owner or operator must note the time, date, and details of any incident that requires implementing the contingency plan in the operating record. Within fifteen days after the incident, the owner or operator must submit a written report on the incident to the department. The report must include the following:
a. The name, address, and telephone number of the owner or operator;
b. The name, address, and telephone number of the facility;
c. The date, time, and type of incident (for example, fire, explosion);
d. The name and quantity of materials involved;
e. The extent of injuries, if any;
f. An assessment of actual or potential hazards to human health or the environment, where this is applicable; and
g. The estimated quantity and disposition of recovered material that resulted from the incident.

N.D. Admin Code 33-24-05-998

Amended by Administrative Rules Supplement 2016-359, January 2016, effective 1/1/2016.

General Authority: NDCC 23-20.3-03

Law Implemented: NDCC 23-20.3-03, 23-20.3-04, 23-20.3-05