N.Y. Comp. Codes R. & Regs. tit. 6 § 645-5.4

Current through Register Vol. 46, No. 25, June 18, 2024
Section 645-5.4 - Commission action on applications
(a) Following its review of an application, the commission shall mail notice of its determination of completeness or incompleteness to the applicant.
(b) If the application is determined to be incomplete, the notice shall include a brief statement indicating all identifiable areas of incompleteness.
(c) If the application is determined to be complete, the notice shall state:
(1) the applicant's name;
(2) a brief description of the proposed project and its location, including the real property map section, block and lot;
(3) whether the project is major or minor;
(4) a list of all commission permits for the project for which application has been made, and identification numbers for those applications;
(5) the name and telephone number of the commission representative and, where applicable, of any lead agency representative to contact for further information;
(6) the status of environmental reviews undertaken under SEQR, including identification of lead agency, a positive or negative determination of significance, and whether the action is Type I, unlisted, Type II, exempt, or excluded, as defined in 6 NYCRR Part 617 or Subpart 645-3 of this Part; and
(7) if public notice is required, the deadline (not less than 15 calendar days after the date of publication) for submission of written comments on the application, and the deadline (not less than 30 calendar days after publication) for submission of comments on the DEIS if one has been prepared.

N.Y. Comp. Codes R. & Regs. Tit. 6 § 645-5.4