Current through Register Vol. 46, No. 45, November 2, 2024
Section 259.3 - Notification of proposed construction(a) Initial report. At least 90 days prior to the start of construction or reconstruction of any LNG facility, each gas corporation shall file with the Office of Gas and Water of the Department of Public Service, a letter of intent, together with the design data and specifications for the proposed facility. The Office of Gas and Water staff shall also be promptly notified of any significant change affecting the initial filing which may occur after submission of the initial filing.(b) Final report. Before any LNG facility is placed in operation, a report shall be filed with the Office of Gas and Water of the Department of Public Service certifying that the facility has been constructed and tested in accordance with the requirements of this Part. A summary of the results of all tests shall accompany the final report.N.Y. Comp. Codes R. & Regs. Tit. 16 § 259.3