N.Y. Comp. Codes R. & Regs. tit. 16 § 255.743

Current through Register Vol. 46, No. 42, October 16, 2024
Section 255.743 - Pressure-limiting and -regulating stations: testing relief device
(a) Overpressure protection devices shall be tested in place annually to determine if they are in proper working condition. They are to be subjected to such maintenance and overhaul as may be indicated by said tests. Overpressure protection devices used solely for the protection of "fuel piping" as, for example, to compressors at the compressor stations, shall be tested and inspected in like manner.
(b) Nonworking monitoring regulator equipment shall be subject to an annual performance test and shall be internally inspected and overhauled if so required by the results of the test.
(c) An annual review of the required capacity of the relieving equipment at each station shall be made and these required capacities compared with the calculated or experimentally determined recorded relieving capacity of the installed equipment for the operating conditions under which it works.
(d) If the relieving equipment is of insufficient capacity, a new or additional device shall be installed to provide the additional capacity required or the station regulator capacity reduced commensurate with the existing relief capacity.

N.Y. Comp. Codes R. & Regs. Tit. 16 § 255.743