Section 255.329 - Installation of plastic pipelines by trenchless excavation

Plastic pipelines installed by trenchless excavation must comply with the following:

(a) Each operator must take practicable steps to provide sufficient clearance for installation and maintenance activities from other underground utilities and/or structures at the time of installations.
(b) For each pipeline section, plastic pipe and components that are pulled through the ground must use a weak link, as defined by section 255.3 of this Part, to ensure the pipeline will not be damaged by any excessive forces during the pulling process.