Section 255.329 - Installation of plastic pipelines by trenchless excavationPlastic pipelines installed by trenchless excavation must comply with the following:
(a) Each operator must take practicable steps to provide sufficient clearance for installation and maintenance activities from other underground utilities and/or structures at the time of installations.(b) For each pipeline section, plastic pipe and components that are pulled through the ground must use a weak link, as defined by section 255.3 of this Part, to ensure the pipeline will not be damaged by any excessive forces during the pulling process.N.Y. Comp. Codes R. & Regs. Tit. 16 § 255.329