Current through Register Vol. 46, No. 45, November 2, 2024
Section 14-9.30 - Requirements for drains(a) Ample drains shall be provided where required to permit complete drainage of all piping, superheaters, water walls, water screens, integral economizers, high temperature water boilers, and all other boiler components in which water may collect. Piping shall conform to the requirements of ASME.(b) Each superheater shall be equipped with at least one drain so located as to most effectively provide for the proper operation of the apparatus.(c) Each high-temperature water boiler shall have a one inch minimum pipe size bottom drain connection in direct connection with the lowest water space practical for external piping conforming to the requirements of ASME.N.Y. Comp. Codes R. & Regs. Tit. 12 §§ 14-9.30