Section 4.10.14.13 - REPORTING STANDARDS
A. The permittee may submit to HPD one copy of a preliminary report on the results of the excavation including relevant maps, drawings, photographs and other documents for review and acceptance by HPD prior to construction and when a final report cannot be completed before construction.
B. A final report and associated records, including but not limited to archaeological site records, list of collections, and photographs, on the excavations shall be submitted to HPD within one year of the completion of the excavations or the date approved by the CPRC. If HPD has not received a copy of the report within the permit period, HPD shall contact the permittee. If the excavations are part of a larger project that includes sites on state land, the final report shall be prepared consistent with 4.10.16.14 NMAC for test excavation projects or 4.10.21.12 NMAC for excavation projects.
C. All reports shall be reviewed by HPD for technical accuracy and completeness.
(1) If HPD review reveals that the proposed investigations were not completed consistent with the application and stipulations contained on the approved permit, HPD will notify the permittee of the deficiencies and request that the permittee amend the report to correct the deficiencies and resubmit the report.
(2) Failure by the permittee to conduct the permitted investigation according to standards or stipulations or to submit required reports in a timely manner or to amend report deficiencies as identified by HPD shall be documented as unacceptable performance pursuant to 4.10.8.21 NMAC.

N.M. Code R. § 4.10.14.13