N.M. Code R. § 20.2.99.114

Current through Register Vol. 35, No. 11, June 11, 2024
Section 20.2.99.114 - FREQUENCY OF CONFORMITY DETERMINATIONS - PROJECTS

FHWA/FTA projects must be found to conform before they are adopted, accepted, approved, or funded. Conformity must be redetermined for any FHWA/FTA project if one of the following occurs:

(A) a significant change in the project's design concept and scope;
(B) three (3) years elapse since the most recent major step to advance the project including;
(1) NEPA process completion;
(2) start of final design;
(3) acquisition of a significant portion of the right-of-way; and
(4) construction (including federal approval of plans, specifications and estimates); or
(C) initiation of a supplemental environmental document for air quality purposes.

N.M. Code R. § 20.2.99.114

12/14/94; 11/23/98; 20.2.99.114 NMAC - Rn, 20 NMAC 2.99.114; A, 10/15/05