Section 20.2.99.108 - NOTIFICATION PROCEDURES FOR ROUTINE ACTIVITIES

Notification of affected agencies (including those listed in Paragraph (1) of Subsection C of 20.2.99.102 NMAC) of transportation plan or TIP amendments which merely add or delete exempt projects shall be the affirmative responsibility of NMDOT or the MPO. Such notification shall be provided not later than 30 days prior to the preparation of the final draft of the document or decision. This process shall include:

A. notification of the affected agencies (including those listed in Paragraph (1) of Subsection C of 20.2.99.102 NMAC) early in the process of decision on the final document; and
B. supplying all relevant documents and information to the affected agencies (including those listed in Paragraph (1) of Subsection C of 20.2.99.102 NMAC).

N.M. Code R. § 20.2.99.108

Adopted, New Mexico Register, Volume XXV, Issue 16, August 29, 2014, eff. 9/15/2014