Section 19.8.11.1120 - POST-PERMIT ISSUANCE INFORMATION REQUIREMENTS FOR PERMITTEES
A. Within 30 days after the issuance of a cessation order in accordance with 19.8.30.3000 NMAC, or a federal cessation order issued in accordance with 30 CFR 843.11, the permittee must provide or update all the information required under Subsection C and D of 19.8.7.701 NMAC.
B. The permittee does not have to submit information under Subsection A of 19.8.11.1120 NMAC if a court of competent jurisdiction grants a stay of the cessation order and the stay remains in effect.
C. Within 60 days of any addition, departure, or change in position of any person identified in Subsections C or D of 19.8.7.701 NMAC, the permittee must provide:
(1) the information required under Subsections C or D of 19.8.7.701 NMAC; and
(2) the date of any departure.

N.M. Admin. Code § 19.8.11.1120

19.8.11.1120 NMAC - N, 08-31-2010