N.M. Code R. § 19.25.20.106

Current through Register Vol. 35, No. 11, June 11, 2024
Section 19.25.20.106 - METERING OF NON-PUEBLO AND PUEBLO WELLS
A. Pursuant to the well metering order for the NPT basin issued by the state engineer, each well owner of record shall install a totalizing meter in accordance with the requirements of Subsection C of 19.27.5.13 NMAC and any additional requirements of the state engineer, to measure the amount of water diverted from each well.
B. Each Pueblo shall install a totalizing meter to measure the amount of water diverted from each well located on Pueblo land, consistent with the well metering order for the NPT basin issued by the state engineer.
C. Each well owner of record shall file a meter installation and inspection report with the state engineer in accordance with the requirements of Subsection C of 19.27.5.13 NMAC and any additional requirements of the state engineer. Pursuant to the settlement agreement and the final decree, each Pueblo shall file a report with the state engineer consistent with the requirements of Subsection C of 19.27.5.13 NMAC.
D. Each well owner of record shall submit meter readings to the state engineer in accordance with the requirements of Subsection C of 19.27.5.13 NMAC and any additional requirements of the state engineer. Pursuant to the settlement agreement and the final decree, each Pueblo shall file a report with the state engineer consistent with the requirements of Subsection C of 19.27.5.13 NMAC.
E. The requirements of this Section shall also apply to all new wells drilled on Pueblo land after the effective date of this rule and a meter shall be installed on such wells at the time the well is drilled.

N.M. Code R. § 19.25.20.106

Adopted by New Mexico Register, Volume XXVIII, Issue 17, September 12, 2017, eff. 9/12/2017