N.M. Admin. Code § 17.9.572.14

Current through Register Vol. 35, No. 21, November 5, 2024
Section 17.9.572.14 - ANNUAL RENEWABLE ENERGY ACT PLAN
A. An annual Renewable Energy Act plan shall include plan year and next plan year data. The plan year shall be presented for commission approval and the next plan year shall be presented for informational purposes.
B. On or before July 1 of each year, each public utility shall file with the commission an annual Renewable Energy Act plan. The filing schedule shall be staggered, as follows, with each of the investor-owned utility filings occurring one month apart, the last filing to be made July 1of each year. The utilities shall file alphabetically each year (el paso electric company shall file on May 1; public service company of New Mexico shall file on June 1; and southwestern public service company shall file on July 1 each year).
C. The annual Renewable Energy Act plan shall include:
(1) testimony and exhibits providing a full explanation of the utility's determination of the plan year and next plan year renewable portfolio standard and reasonable cost threshold;
(2) the cost of procurement in the plan year and the next plan year for all new renewable energy resources required to comply with the renewable portfolio standard selected by the utility pursuant to 17.9.572.10 NMAC;
(3) the amount of renewable energy the public utility plans to provide in the plan year and the next plan year required to comply with the renewable portfolio standard;
(4) testimony and exhibits demonstrating how the cost and amount specified in Paragraphs (2) and (3) of this subsection were determined;
(5) testimony and exhibits demonstrating the plan year and next plan year procurement amounts and costs expected to be recovered by the utility;
(6) the capital, operating, and fuel costs on a per-megawatt-hour basis during the preceding calendar year of each nonrenewable generation resource rate-based by the utility, or dedicated to the utility through a power purchase agreement of one year or longer, and the nonrenewable generation resources' carbon dioxide emissions on a per-megawatt-hour basis during that same year;
(7) testimony and exhibits demonstrating the plan year and next plan year procurement amounts and costs expected to be recovered by the utility if limited by the reasonable cost threshold;
(8) testimony demonstrating that the cost of the proposed procurement is reasonable compared with the price of electricity from renewable resources in the bids received by the public utility to recent prices for comparable energy resources elsewhere in the southwestern united states;
(9) testimony regarding strategies used to minimize costs of renewable energy integration, including location, diversity, balancing area activity, demand-side management, rate design, and load management;
(10) testimony demonstrating that the portfolio procurement plan is consistent with the integrated resource plan and explaining any material differences;
(11) testimony demonstrating that acceptable system reliability will be maintained with the proposed new renewable resource additions;
(12) information, including exhibits, as applicable, that demonstrates that the proposed procurement was the result of a competitive procurement that included opportunities for bidders to propose purchased power, facility self-build, or facility build-transfer options;
(13) demonstration that the plan is otherwise in the public interest, considering factors such as overall cost and economic development opportunities;
(14) a mechanism, with supporting testimony, to prevent the public utility's voluntary program customers from being subject to charges by the public utility to recover RPS compliance costs pursuant to Subsection B of Section 62-16-7 NMSA 1978; and
(15) any other information the commission may deem necessary.
D. In addition to electronically filing and serving in accordance with 1.2.2 NMAC, a public utility shall serve notice and a copy of its annual renewable energy plan filing by first class mail on renewable resource providers requesting such notice from the commission, the New Mexico attorney general, and the intervenors in the public utility's most recent rate case. A public utility shall also post on its website the most recent and the pending annual Renewable Energy Act plans.

N.M. Admin. Code § 17.9.572.14

17.9.572.14 NMAC - Rp, 17.9.572.16 NMAC, 5-31-13; A, 5-15-14, Adopted by New Mexico Register, Volume XXXII, Issue 09, May 4, 2021, eff. 5/4/2021, Adopted by New Mexico Register, Volume XXXIV, Issue 04, February 28, 2023, eff. 2/28/2023