N.J. Admin. Code § 7:27-16.19

Current through Register Vol. 56, No. 12, June 17, 2024
Section 7:27-16.19 - Application of cutback and emulsified asphalts
(a) On or after April 16, 2009, no person shall use or apply, during the period from April 16 through October 14, cutback asphalt or emulsifed asphalt, unless:
1. The asphalt contains no greater than 0.1 percent VOC by weight; or
2. The asphalt produces no greater than 6.0 milliliters of oil distillate, in accordance with ASTM Method D244, Standard Test Methods and Practices for Emulsified Asphalts, or AASHTO T 59, Standard Method of Test for Testing Emulsified Asphalts, both as supplemented or amended and incorporated herein by reference. ASTM Method D244 is available from the American Society for Testing and Materials (ASTM), 100 Barr Harbor Drive, Post Office Box C700, West Conshohocken, Pennsylvania 19428-2959, or from its website http://www.astm.org. AASHTO T 59 is available from the American Association of State Highway and Transportation Officials (AASHTO), 444 North Capitol Street N.W., Suite 249, Washington, DC 20001, or from its website http://www.transportation.org.
(b) On or after April 16, 2009, no person shall store cutback asphalt or emulsified asphalt during the period from April 16 through October 14 that does not meet the requirements at (a) above, unless the cutback asphalt or emulsified asphalt is stored in a sealed container.

N.J. Admin. Code § 7:27-16.19

Amended by R.1992 d.102, effective 3/2/1992 (operative March 28, 1992).
See:23 N.J.R. 1858(b), 24 N.J.R. 792(a).
Addressed EPA-identified deficiencies; "VOS" changed to "VOC" throughout.
Recodified from 7:27-16.7 and amended by R.1994 d.313, effective 6/20/1994 (operative July 26, 1994).
See:25 N.J.R. 3339(a), 26 N.J.R. 2600(a).
Repeal and New Rule, R.2009 d.137, effective 4/20/2009 (operative May 19, 2009).
See: 40 N.J.R. 4390(a), 41 N.J.R. 1752(a).
Section was "Application of cutback and emulsified asphalts".