Current through Register Vol. 56, No. 21, November 4, 2024
Section 7:26E-5.5 - Remedial action workplan requirements(a) The person responsible for conducting the remediation shall prepare and submit to the Department prior to implementation, a remedial action workplan for each area of concern requiring a remedial action, unless a final remediation document for unrestricted use is filed with the Department within one year after the earliest applicable requirement to remediate, pursuant to N.J.A.C. 7:26C-2.2.(b) The person responsible for conducting the remediation shall include the following in each remedial action workplan for each area of concern:1. A summary of the findings and recommendations from the remedial investigation report prepared pursuant to 7:26E-4.9;2. A description of any interim remedial measures previously implemented;3. The identification of each area of concern where the remedial action will be implemented, including:i. The horizontal and vertical extent of the area to be remediated correlated to the extent of contamination; andii. The volume of the contamination to be treated or removed for each environmental medium;4. A detailed description of the remedial action and the remedial technology to be used for the area of concern, including the results of any bench scale, pilot test or design studies;5. Identification of all applicable remediation standards;6. A plan to evaluate the effectiveness of the remedial action;7. A perimeter air monitoring and action plan to be implemented during a remedial action, if applicable, designed to monitor and control off-site excursion of dust, vapor and odors;8. A list of all required permits;9. A fill use plan that complies with 7:26E-5.2, if applicable;10. A plan to restore the site after implementing the remedial action, if applicable; and11. The proposed completion date of the remedial action and a schedule of the remedial action for the initiation and completion of each remedial action task, pursuant to the required regulatory timeframe at 7:26E-5.8.(c) The person responsible for conducting the remediation shall submit a revised remedial action workplan or remedial action workplan addendum prepared pursuant to this section: 1. When a remedial action does not perform as designed; or2. To upgrade or change the selected remedial action. N.J. Admin. Code § 7:26E-5.5
Amended by 50 N.J.R. 1715(b), effective 8/6/2018