N.J. Admin. Code § 7:14-2.8

Current through Register Vol. 56, No. 11, June 3, 2024
Section 7:14-2.8 - Payments to contractors
(a) At least 20 days before each monthly progress payment falls due for approval (but not more often than once per month), the contractor will submit to the engineer a partial payment estimate filled out and signed by the contractor covering the work performed during the period covered by the partial payment estimate and supported by such data as the engineer may reasonably require. Where any specific item(s) in the partial payment estimate is in dispute, the engineer may delete those costs from the estimate and approve the acceptable portion of the payment request. Payment requested for stored materials and/or equipment shall be subject to the following conditions being met or satisfied:
1. The materials and/or equipment shall be received in a condition satisfactory for incorporation in the work.
2. The materials and/or equipment shall be stored in such manner that they will not be damaged due to weather, construction operations or any other cause.
3. An invoice from the supplier shall be furnished for each item on which payment is requested.
4. The contractor shall furnish written proof from the supplier of 90 percent payment for the materials and/or equipment no later than 30 days after receipt of payment for same from the owner. The owner shall have the right to deduct from the next payment estimate an amount equal to the payment for said material and/or equipment if reasonable and adequate proof is not submitted.
(b) The contractor warrants and guarantees that title to all work, materials, and equipment covered by an Application for Payment, whether incorporated in the project or not, will pass to the owner upon the receipt of such payment by the contractor free and clear of all lien, claims, security interests or encumbrances (except 10 percent retention which may be withheld from suppliers and subcontractors to guarantee completion and performance). The engineer will after receipt of each partial payment estimate either indicate in writing his approval of payment and present the partial payment estimate to the owner, or return the partial payment estimate to the contractor indicating in writing his reasons for refusing to approve payment. In the latter case, the contractor may make the necessary corrections and resubmit the partial payment estimate. The owner shall review the partial payment estimate at its next regularly scheduled meeting and, if approved, payment shall be made available to the contractor within five days. The owner shall retain not more than two percent of the amount of each payment claimed. In accordance with EPA regulations, prime contractors are also required to make prompt payment to subcontractors and suppliers for eligible construction, material, and equipment costs. Generally, payments of all valid subcontractor and supplier requests for payment should be satisfied prior to the next succeeding request for progress payment by the prime contractor.
(c) When the work is substantially complete (Operational or Beneficial Occupancy), the withheld amount shall be further reduced below two percent but not less than twice the current market value of the work yet to be completed. On completion and acceptance of a part of the work on which the price is stated separately in the Contract Documents, payment shall be made in full including retained percentages, less authorized deductions. The contractor or owner may request assistance and guidance from the Department on disputes regarding retainage.
(d) "Substantial completion" as used in the context of this section shall mean satisfactory completion of major portions of the contract work, including inspection and testing, so that the facility may be turned over to the owner for its intended use or occupancy. The engineer shall certify the date of substantial completion and that date shall establish the beginning date of the warranty/guarantee period unless a prior date has been established.

N.J. Admin. Code § 7:14-2.8